East Lycoming School District must scale back project
Trending
HUGHESVILLE -- East Lycoming School Board will need to reject bids amounting to $44.6 million for the Ashkar Elementary School rebuild at its next meeting.
The district officials say they have a $25 million bond and $5 million line of credit. Total project cost as bid was $44.6 million.
The district has a "maximum of $33 million to spend," board member Donna Gavitt said.
The present eight directors and administration will continue to consult with Marotta/Main and Fidevia, which are the architectural and the construction firms that are guiding the district through the bidding process.
"Clearly it is not a viable project," Dr. Mark Stamm, superintendent, said.
That much was realized at the meeting as the cost breakdown was provided: General construction, $25.2 million; electrical, $2.9 million; mechanical construction, $7.6 million; plumbing, $2 million; fire protection, $673,287.
Additional costs estimates included: Asbestos abatement, $280,000; playground equipment, $224,899; gym bleachers, $360,000; furniture, $591,715; security cameras and door access, $78,372 and phone/intercom system, $39,534. Soft costs (fees, permits, testing, construction supervision etc.), $3 million and construction contingency (General and Electrical Primes only), $1.4 million.
"We want a learning environment," Stamm said, adding the district officials had to make hard choices and bring back a viable project.
For example, the proposed gymnasium may or may not be able to be accomplished and may have to be an add-on project in the future.
Additionally, should more bidders submit bids for consideration, such as eight compared to two companies, that competition can help the district with its project cost estimates. That question was posed by board member Rose Trevouledes.
Stamm noted there is a need for this project to have an academic purpose first and at the end of the project the district wants a building that will last for generations.
Currently, as the bid came in, there is no project, he said, but there is an intention by the administration and board to review what can be deducted and reconfigured to ensure the elementary rebuild is done as desired and economically feasible.