Appeal filed against ‘deemed approval’ of data center in Muncy Township
The proposed data center project in Muncy Township is starting to get tied up in the courts. Since April 28, it has been widely reported that Danko Holdings II LP and Fishlips LLC. have applied for conditional use for three data center buildings, two 14-pod facilities, one eight-pod facility, water storage tanks, a water treatment facility, a substation, and auxiliary structures near Yetter Road and John Brady Drive. In July, however, when the township had not held a conditional use hearing within 60 days of the developer filing April 28, nor rendered a determination on the data ...